Skip to content

Oldenburg's Railway Station Expansion Project Delays Completion by Two Additional Years

Delay in completion of Oldenburg's Train Hall Renovation Extends to Two Additional Years

Westoverledingen's steel construction firm is currently crafting the steel structures for...
Westoverledingen's steel construction firm is currently crafting the steel structures for Oldenburger Train Hall, located in the Ostfriesland region (Leer district). [Photo available]

Construction Delays Plague Oldenburg's Historic Train Hall Renovation

Oldenburg's Train Hall Redevelopment Delayed by Two Extra Years - Oldenburg's Railway Station Expansion Project Delays Completion by Two Additional Years

Let's dive right in: unexpected corrosion damage has sent Deutsche Bahn's (DB) schedule for renovating Oldenburg's iconic train hall, the last remaining historic one in Lower Saxony, off the rails. From the initial 2027 finish date, we're now looking at completion by 2029, according to DB. Brace yourselves, travelers, as temporary constraints may appear with some platforms getting construction attention.

Stepping back in time, the esteemed train hall within the station building hails from 1915. Due to the wobbly structure's inadequate support, the three hall ships have been undergoing renovation since last year. A steel manufacturer in East Frisia's Westoverledingen, Leer district, has been hard at work on the upgrades for these steel beams.

Now, let's get to the meaty part: "Tests and inspections on the steel components at platform 7/8 painted a grim picture," said DB's project manager Felix Burckhardt. "Crippling corrosion damage was discovered, especially at the connection points and areas under previous attachments." This, of course, means additional work will be required on the other two hall ships over tracks 3/4 and 5/6.

With an estimated 80 million euros being pumped into this makeover, DB intends to stay within budget despite the extended renovation timeline. Most of the dough will be allocated to dismantle, refurbish, and reinstall the three hall ships, including the glass roofs and their supporting elements.

As for Oldenburg's expectations, the chief building officer Christine-Petra Schacht sees a bright future for the Jugendstil and Heimatstil-style hall that welcomes around 25,000 passengers every day, owned by Deutsche Bahn. "While the delay is certainly unfortunate for everyone involved," Schacht noted, "given the unforeseen damage to the steel beams, it's also understandable."

According to DB's renovation plan, the hall ship at platforms 5/6 will be the first to receive the full treatment, targeting completion by mid-2027. Elsewhere, work is in motion. For example, the foundation of the hall ship 7/8 is getting spruced up as we speak, and by late summer, the hall ship 3/4 will be disassembled. During the renovation, platform 5/6 is also in line for an extension of about 50 meters.

OldenburgRenovation projectTrain hallConstruction projectDBDeutsche BahnLeer

Community aid could be organized to support travelers during the temporary constraints caused by the construction in Oldenburg's train hall, helping finance alternatives for transportation if needed. Meanwhile, vocational training programs could be initiated for the workers involved in the renovation process, ensuring they possess the necessary skills for constructing, repairing, and maintaining various components within the train hall industry.

Read also:

    Latest